Crosses indicate where
static occupations take
place.
2.
3.
Note that the content of the Site ID field is incremented by
1 after ending static occupation on a point (increment: 0
to 9, then A to Z, then 0.. again, etc.). You can however
change the Site ID between any two occupation times by
pressing the LOG key (not the on-screen Log button) and
editing the Site ID field.
13.Move to the next point and resume the above two steps
until all the points have been visited.
14.Tap Done after surveying the last point. This completes
the data collection phase.
Running a Kinematic Survey
This chapter describes a typical Kinematic survey in which
initialization is performed on a known point (The fastest ini-
tialization method.)
Base Setup and Operation
The base is setup and operated in the same way as it is in stat-
ic surveys (see page 43).
Rover Setup
Install the unit on its range pole:
1. Mount the GNSS antenna on the pole
2. Attach the field bracket onto the pole
3. Place the ProMark3 receiver into the field
bracket
4. Connect the GNSS antenna to the unit
using the cable provided.
5. Measure the antenna height.
1.
4.