INSTALLATION
5.
NOTE The EBM(s) must be installed to the right of the UPS as shown in Figure 7. Joining
brackets are required for installations with two or more cabinets.
18
EATON Powerware
www.powerware.com
Figure 6. UPS Cabinet with Pedestals
Carefully position the cabinets upright (see Figure 7).
Figure 7. Tower UPS with an EBM
®
9125 Two-in-One UPS (5000/6000 VA) User's Guide