Vent Clearances And Framing; Pipe Clearances To Combustibles; Wall Penetration Framing - Heat & Glo XLR-N-AU Owner's Manual

Fireplace
Hide thumbs Also See for XLR-N-AU:
Table of Contents

Advertisement

8 8

Vent Clearances and Framing

A. Pipe Clearances to Combustibles
WARNING! Risk of Fire! Maintain air space clearance to
vent. DO NOT pack insulation or other combustibles:
• Between ceiling fi restops
• Between wall shield fi restops
• Around vent system
Failure to keep insulation or other material away from
vent pipe may cause over heating and fi re.
Note: Heat shields MUST overlap by a minimum of 38 mm.
• SLP heat shield - designed to be used on a wall 111 mm to 194 mm thick.
• If wall thickness is less than 111 mm the existing heat shields must be field trimmed.
If wall thickness is greater than 194 mm a DVP-HSM-B will be required.
(SLP Pipe Shown)
Heat
Shield
76 mm
top clearance
25 mm
clearance around
vertical sections
* When using SLP pipe, minimum clearances from the vent pipe to combustible materials
at inside wall firestops are:
Figure 8.1 Horizontal Venting Clearances To Combustible
Materials
30
76 mm
top clearance *
Heat
Shield
25 mm
clearance
Wall
bottom & sides
Shield
Firestop
WALL
Top: 64 mm
Bottom: 13 mm
Sides: 25 mm
Heat & Glo • XLR-N-AU, XLR-PB-AU • 2198-906 Rev. C • 3/10
B. Wall Penetration Framing
Combustible Wall Penetration
Whenever a combustible wall is penetrated, you must
frame a hole for the wall shield fi restop(s). The wall shield
fi restop maintains minimum clearances and prevents cold
air infi ltration.
• The opening must be framed on all four sides using the
same size framing materials as those used in the wall
construction.
• SLP pipe - A wall shield fi restop must be placed on each
side of an interior wall. A minimum 38 mm overlap of at-
tached heat shields must be maintained.
• See Section 10.K. for information for regarding the in-
stallation of a horizontal termination cap.
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by noncom-
bustible materials such as concrete, a hole with diameter
254 mm greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall
shield fi restop is only required on one side and no heat
shield is necessary.
DO NOT PACK WITH
INSULATION OR
OTHER MATERIAL
254 mm
254 mm
A
A*
1220 mm
* Shows center of vent framing hole for top venting. The center of the hole
is one 254 mm above the center of the horizontal vent pipe.
Figure 8.2 Wall Penetration
B
B
1200 mm

Advertisement

Table of Contents
loading

This manual is also suitable for:

Xlr-pb-au

Table of Contents