Boiler installation

7
Boiler installation
This chapter describes how to install the boiler. This
includes the following tasks:
– Connecting the heating system
– Electrical connection
– Fuel supply connection
7.1

Preparing for installation

Unpack all boxes and containers and check all parts
against the packing lists to make sure that everything
has been supplied.
USER NOTE
Every boiler is carefully inspected and
tested before it leaves the factory.
However, if you discover any damage or
missing parts, please inform the supplier
immediately. Before disposing of packing
material, make sure that no parts are still
in it.
USER NOTE
The gas connection pipe is designed for a
gas connection on the right side.
If the gas connection is from the left,
the gas connection pipe must be
completely unscrewed, turned 180°
and then sealed again.
Check the connection for leaks.
7.2

Installing the draft hood and the main drain

Fasten draft hood to the exhaust manifold with the
eight retaining screws (included).
12
Installation and maintenance instructions Logano G334 X gas-fired boiler • Issue 09/2005
1
Fig. 6
Installing draft hood, Logano G334 X
1 Retaining screws on exhaust manifold