4.2

Clearances

Position the boiler with the recommended wall clearances. Reducing the
minimum clearances makes the boiler more difficult to access.
The base or foundation on which the boiler is to stand must be perfectly
flat and level. The boiler may be installed on a combustible base, but not
on carpet.
Wall clearance
Dimension
inches (mm)
A
33 (840)
B
6 (155)
C
2 (50)
Table 6 Wall clearances
Where applicable, allow extra wall clearances for
additional components such as DHW storage tank, pipe
connections, flue silencer or other flue components, etc.
A space of at least 33 inches (840 mm) is required in front of the boiler
with the door open to allow sufficient accessibility for operation and
maintenance. When the door is closed, a minimum clearance of 2 inches
(50 mm) is required at the front and sides, a wall clearance of 6 inches
(155 mm) is also required for the flue pipe and 30 inches (762 mm)
clearance to the ceiling.
Fig. 6 Wall clearances in the boiler room
[1]
Closed door
[2]
Open door
4.3

Leveling the boiler

The boiler must be leveled horizontally and vertically to prevent air
pockets forming inside.
▶ Level the boiler vertically and horizontally, inserting metal shims
underneath as required.
NOTICE: Risk of system damage due to contamination!
▶ Protect boiler connections from damage and dirt if the
boiler is not to be installed immediately.
Logano G234X – 6 720 804 886 (2012/08)
Fig. 7 Leveling the boiler (example)
5

Boiler installation

This section details how to install your boiler correctly. This involves the
following steps:
• Flue gas connection
• Heating circuit connection
• Making the electrical connections
• Connecting the fuel supply
5.1

Preparing for installation

▶ Unpack all cartons and boxes.
▶ Using the included packing list, check to be sure that you have all the
included parts.
Every boiler is carefully inspected and tested before it
leaves the factory. However, if you discover any damage
or missing parts, please inform the supplier
immediately. Before disposing of packing material,
make sure that no parts are still in it.
Route the gas connection towards the left
The gas connection pipe is designed for a gas connection
on the right side.
▶ Loosen the screws on the gas connection pipe completely.
▶ Attach the gas connection pipe shifted by 180° and seal.
▶ Carry out the leak test.