Finishing

A. Mantel Projections
This appliance is approved to be installed with a clearance
to the ceiling and/or other projections of 34-3/8 inch
minimum from the top of the fi replace (see Figure 11.1).
FRAMING
MEMBER
FIRESTOP
34-3/8 in.
TO CEILING
AND/OR MANTEL
TOP
OF UNIT
Figure 11.1 Clearances to mantels or other combustibles
above appliance
B. Facing Material
WARNING
Fire Risk.
Do NOT obstruct air inlet or outlet grilles.
Do NOT modify grilles.
• Modifying or covering grilles could cause
temperature rise and fi re hazard.
Finishing materials must not interfere with:
• Air fl ow through grilles or louvers.
• Operation of louvers or doors.
• Access for service.
WARNING
Fire Risk.
Finish all edges and fronts to clearances and
specifi cations listed in manual.
• Install combustible materials only up to specified
clearances on top, front and side.
• Seal joints between the fi nished wall and appliance top
and sides using only a 300º F minimum sealant.
30
SLIP
SECTION
COMBUSTIBLE
MATERIAL
GLASS
TUBE
41-3/8 in.
(+0 to -1/2 in.)
Heat & Glo • Cyclone-Cust • 2061-900 Rev. L • 10/08
NON-COMBUSTIBLE
COMBUSTIBLE
ON SIDES
0 IN.
SEALANT MATERIAL
Figure 11.2 Facing Diagram
Sheetrock or other fi nishing materials can be brought to
within 0 inches on the sides and bottom.
Finishing materials for the top of the fi replace base must
be noncombustible and removable for access to controls.
All clearances must be maintained (see Figure 11.3).
Ø 9-1/8 in. MIN.
OPENING
Figure 11.3
0 IN.
MATERIAL MUST BE
NON-COMBUSTIBLE
AND REMOVABLE
TOP MUST
MAINTAIN 1/2 in.
CLEARANCE
1/2 in.