1) Determine the total thickness of facing
material (e.g. drywall plus ceramic tiles) to
allow the fi nished surface to be fl ush with
the front of the unit. Total facing thickness
can vary from 1/2" (13mm) to 1-1/4" (32mm)
thick.
Install Side Nailing Strips, and Top Facing
Support before unit is slipped into position.
See "Unit Assembly Prior to Installation"
Section
2) Frame in the enclosure for the unit with
framing material.
Vertical Termination or
Vertical Rise with Horizontal
Termination
For Both Rigid & Flex
NOTE: If this is an outside corner, the
minimum distance between the vent and the
outside corner is 6" (15cm) with AstroCap
termination cap or 12" (30cm) with Rigid Vent
termination cap. (For example Dura-Vent).
NOTE: Framing is different when using the
faceplate option.
See framing section when using faceplate in
this manual.
®
Regency
P33-4 Zero Clearance Direct Vent Gas Fireplace

FRAMING AND FINISHING

Rear Termination
For Rigid Vent
For Flex Vent
For Both Rigid & Flex
NOTE: If this is an outside corner, the minimum
distance between the vent and the outside
corner is 6" (15cm) with AstroCap termination
cap or 12" (30cm) with Rigid Vent termination
cap. (For Example Dura-Vent).
3) For exterior walls, insulate the enclosure to
the same degree as the rest of the house,
apply vapour barrier and drywall, as per
local installation codes. (Do not insulate
the fi replace itself.)
4) The top of the unit must not be closer than
30" (762mm) to the ceiling.
5) Combustible material may be brought up to
the top and sides of the unit and be covered
with ceramic tiles, bricks, rock or other
suitable combustible fi nishing materials.
Note: The unit does not have to be completely
enclosed in a chase. The clearance on
top of the unit is 0" to the standoffs so
combustible building materials can be
laid directly on top of the standoffs.
You must maintain clearance from
the vent to combustible materials
for fl ex or for Rigid Vent (Refer to
"Clearances" Section).
INSTALLATION
Rigid Vent
Minimum Clearances
Top Header
10" (254mm)
1/2"
dia. Hole through
(13mm)
wall for Dura-Vent
Drywall
1-1/2"
(38mm)
4"
3"
16-1/2"
(102mm)
(76mm)
(419mm)
Opening for gas
Minimum
connection
Flex Vent
Minimum Clearances
Top Header
10" (254mm)
1/2"
dia. Hole through
(13mm)
wall for Flex
Drywall
1-1/2"
(38mm)
12-3/4"
4"
3"
(324mm)
(102mm)
(76mm)
Opening for gas
Minimum
connection
6) Use steel studs for framing where the
1-1/2" (38mm) clearance from the vent
to combustible material cannot be
maintained.
The HeatWave Duct Kit has different
clearance and framing requirements,
check the HeatWave manual for details.
13