Outdoor unit installation
Installation summary
1
Install the outdoor unit.
Pressure & leak test
4
Pressure test and leak test.
7
Perform a test run.
Clearances
The outdoor unit must be installed in accordance with the clearances outlined below. Note
maintenance access, there must be sufficient room for installation and maintenance.
>300 mm
on left
Air inlet
greater than
1000 mm in front
2
Connect the refrigerant pipes.
Vacuum hose
5
Evacuate the system.
Wall or obstacle
Air inlet
>600 mm above
Air outlet
3
Connect the wires.
Vacuum pump
6
Charge the system.
>100 mm
from back wall
Maintenance
access
>600 mm
on right
| 25