11 Installation in piping
NOTICE
Connector elements!
▶ The connector elements are not included in the scope of
delivery.
Only use connector elements made of approved materi-
●
als.
Observe permissible tightening torque of the bolts.
●
1. Keep sealing material ready.
2. Carry out preparations for installation (see chapter "Pre-
paring for installation").
3. Ensure clean, undamaged sealing surfaces on the connec-
tion flanges.
4. Align flanges carefully before installing them.
5. Clamp the product centrally between the piping with
flanges.
6. Centre the gaskets.
7. Connect the valve flange and the piping flange using ap-
propriate sealing materials and matching bolting.
8. Use all flange holes.
9. Tighten the bolts diagonally.
10. Re-attach or reactivate all safety and protective devices.
11.7 Installation with clamp connections
Fig. 5: Clamp connection
NOTICE
Gasket and clamp!
▶ The gasket and clamps for clamp connections are not in-
cluded in the scope of delivery.
1. Keep ready gasket and clamp.
2. Carry out preparation for installation (see chapter "Prepar-
ing for installation").
3. Insert the corresponding gasket between the body of the
product and the pipe connection.
4. Connect the gasket between the body of the product and
the pipe connection using clamps.
5. Re-attach or reactivate all safety and protective devices.
GEMÜ 543 eSyStep
OPEN / CLOSE (Code AE)
36 / 68