10 Maintenance
Fig.71
Rinsing the condensate trough
148
11. Rinse out the condensate trough with water through the opening
11
RA-0000308
12. Remove pipe connection
13. Loosen the screwed connection on the condensate connection and
remove the siphon
14. Rinse out the siphon with clear water and reinstall in the reverse order
Danger
12
Risk of life due to escaping flue gas!
Before installing the siphon and commissioning of the gas
condensing boiler, fill the siphon with approx. 1 l water.
15. Check the condensate piping for leaks
13
16. Reinstall the side cladding and cladding front wall
RA-0000309
10.3.6
The CO
be adjusted in accordance with the details in
necessary.
For more information, see
Adjusting CO2 content, page 60
CO2 content at max. output (EC five 400 kW - 540 kW), page 60
CO2 content at min. output (EC five 400 kW - 540 kW), page 60
CO2 content at max. output (EC five 610 kW), page 61
CO2 content at min. output (EC five 610 kW), page 61
10.3.7
All air pressure monitor pipes must be checked, and disconnected and
cleaned with compressed air if necessary.
Important
If the air pressure monitor pipes are disconnected during
maintenance work, they must be reconnected based on the
schematic drawing in the section
air pressure monitor .
For more information, see
Description of the function of the air pressure monitor, page 22
Checking CO
content
2
content must be checked within the scope of maintenance and
2

Checking air pressure monitor pipes

Adjusting CO
content if
2
Description of the function of the
7713465 - 05 - 23102019