Installation and Operation Guide SOLECTRIA
 Verify that the Status Panel illuminates READY and that neither MAINTENANCE nor POWER FAULT
LED is illuminated. If the LEDs are not in this state, see Section 9 Maintenance and Troubleshooting.
 Connect to the XGI virtual HMI. Using a laptop, tablet, or smartphone, connect to the gateway inverter's
WiFi network, XGI-00-006 (see Section 5 User Interface).
 Select the gateway node (in blue) at the top of the list.
 Log in to the inverter (see Section Error! Reference source not found.).
 Select the "First Time Start Wizard" from the menu under "Inverter Configurations".
 Follow the instructions of the "First Time Start Wizard". (See Section 8.1)
 Verify that the Status Panel illuminates READY, NETWORK and COMMUNICATIONS, and POWER.
 Verify that the inverter is operational by checking production using the virtual HMI or a third-party DAS.

Commissioning Test

 Turn on the AC switch located on the right side of the inverter.
 Turn on the DC switch using the handle on the front of the inverter.
 Use the HMI to verify that settings for voltage protection, frequency protection, and autonomous grid
support functions if applicable, are properly configured and compliant with the interconnection
agreement.
 Connect a power quality analyzer, oscilloscope, or other digital voltage measurement device on the
inverter side of the PV system disconnect. The PV system switch is typically the disconnecting means
closest to the point of interconnection. The meter is used to verify voltage and timing requirements
during plant shutdown.
 Once all inverters are operating at a convenient and available power level, open the PV system
disconnect. The inverters are expected to cease operation once the PV system disconnect is open.
Listen for the sound of the AC contractors opening inside the inverters.
 Verify using the meter on the inverter side of the PV system disconnect the absence of voltage within
10 line cycles (0.16s).
 Verify using the XGI virtual HMI absence of grid error message and cessation of power production. This
information is available on the inverter list page and inverter home page.
 Close the PV system disconnect. Verify that voltage has resumed within 5% of nominal.
 Using the XGI virtual HMI, verify initiation of a 5 minute timer before resuming operation. This
information is available on the inverter list page and inverter home page.
 The commissioning and verification test is complete once the inverters have resumed operation 5
minutes after reconnecting the PV system disconnect.