Testing Readiness For Operation - Siemens SIPROTEC 5 V7.80 Operation

Table of Contents

Advertisement

Commissioning
9.3 Initial Startup
Alternatively, you can also verify the parameterization with DIGSI 5. To do this, activate the online mode and
establish connection to the device. Then open the settings comparison between the online device and the
offline device in the project.
During the initialization, the serial number of the device is transferred to the offline project. Alternatively you
can also enter the serial number by hand in the offline device.

Testing Readiness for Operation

9.3.4
By carrying out the points in chapter
operation. If devices are built into cabinets, additional wiring and communication connections are necessary.
Subsequent checks can be made in preparation for the secondary test. To do this, you can make use of
numerous test aids available in the device, which are described in chapter
Device.
Siemens recommends the following procedure in this order:
Testing binary inputs and outputs
²
Check that the connection from the transmission terminal to the device is correct and the binary inputs
and outputs as well.
Testing voltage and current inputs
²
Using multi-phase test equipment, apply the corresponding test quantities and check the results. To do
this, make use of the testing options in the device (see chapter
You can also check the measured values directly on the device by calling up the operational measured
values in the respective function group.
You can also read the operating measured values in the operating software DIGSI 5. Under Online Access
Points, open the assigned device. Under the menu item Measurement, you will find a clear presentation
of the operational measured values in the respective function group.
Checking communication interfaces
²
You can also set the state of signals transferred via communication interfaces. This action allows you to
check, for example, the connection to the systems control. In the communication diagnosis, you will find
helpful information, for example, about data traffic on a communication interface.
Checking time synchronization
²
The device is synchronized by a maximum of 2 independent time sources. In online mode, first click in
the project tree on Device information then on the tab Time information. The delivered specific values
(UTC) of the 1st and 2nd time source (if available) are shown. The internal time of the device which
results from the time information of the active time source is likewise shown.
202
9.3.3 Initializing Device and Verifying Basic
Status, the device is ready for
9.2 Test Suite Integrated in the
9.2.2 Testing Current and Voltage
SIPROTEC 5, Operation, Manual
C53000-G5040-C003-9, Edition 06.2018
Inputs.)