Electrical Hookup Installation; Beater Rotation - Taylor SLIM7 Operator's Manual

Counter top heat treatment soft serve freezer
Table of Contents

Advertisement

NOTICE!
Stationary machines which are not equipped
with a power cord and a plug or another device
to disconnect the machine from the power
source must have an all-pole disconnecting
device with a contact gap of at least 0.125 in.
(3 mm) installed in the external installation.
Machines that are permanently connected to
fixed wiring and for which leakage currents may
exceed 10 mA, particularly when disconnected
or not used for long periods, or during initial
installation, shall have protective devices to
protect against the leakage of current, such as a
GFI, installed by the authorized personnel to the
local codes.
Supply cords used with this machine shall be
oil-resistant, sheathed flexible cable not lighter
than ordinary polychloroprene or other
equivalent synthetic elastomer-sheathed cord
(code designation 60245 IEC 57) installed with
the proper cord anchorage to relieve conductors
from strain, including twisting, at the terminals
and protect the insulation of the conductors from
abrasion.
If the supply cord is damaged, it must be
replaced by the manufacturer, service agent, or
a similarly qualified person, in order to avoid a
hazard.
To the Installer

Electrical Hookup Installation

CAUTION! Avoid injury.
Make sure the machine is electrically
disconnected.
Remove the appropriate panel and locate the
small electrical box at the base of the machine.
Remove the factory-installed cord and strain
relief bushing.
Route incoming permanent wiring through the
7/8 in. (22 mm) hole in base pan.
Connect two power supply leads. Attach ground
(earth) wire to the grounding lug inside the
electrical box.
Make sure the machine is properly grounded
before applying power.

Beater Rotation

NOTICE! Beater rotation must be
counterclockwise as viewed looking into the freezing
cylinder.
The following procedures should be performed by a
Taylor service technician.
To correct rotation on a three-phase machine,
interchange any two incoming power supply lines at
freezer main terminal block only.
To correct rotation on a single-phase machine, change
the leads inside the beater motor. (Follow the diagram
printed on the motor.)
Electrical connections are made directly to the terminal
block in the splice boxes that are mounted mid-level on
the frame channel on the sides of the freezer.
Model 0736
TO THE INSTALLER
1-3
1

Advertisement

Table of Contents
loading

This manual is also suitable for:

736

Table of Contents