Replacing The Meter Body; Figure 25 - St 700 Standard Transmitter - Disassembly For Meter Body Replacement - Honeywell SmartLine ST 700 User Manual

Pressure transmitters
Hide thumbs Also See for SmartLine ST 700:
Table of Contents

Advertisement

17. Restore power if removed.
18. Check the settings of the transmitter Setup and display Setup parameters to make sure that
the transmitter is configured correctly for your application. See the HART/DE User's Manual
(ST 800 #34-ST-25-38, ST 700 #34-ST-25-44) for details on HART and DE transmitters.
Refer to manual #34-ST-25-39 for additional information about Fieldbus transmitters.
19. If applicable, verify External Button Configuration operation. The transmitter is now
available for use.
6.5

Replacing the Meter Body

You can replace the complete meter body, including the process heads, or the meter body only on
certain Differential Pressure (DP), Gauge Pressure (GP), and Atmospheric Pressure (AP) transmitters
by using the existing process head(s). Use the following procedure for meter body-only replacement.
1. Save or record device configuration data.
2. Turn off transmitter power.
3. Remove the transmitter from service, and move it to a clean area before disassembling it.
4. Refer to
Figure
side of the transmitter housing.
Figure 25 – ST 700 Standard Transmitter - Disassembly for Meter Body
Please take appropriate steps to avoid ESD damage when handling the communication
and display module assemblies.
5. If a display is present, press the two snaps along the side, and remove it from the
communication module assembly.
Note: Do not discard or misplace the display/communication connector, it will be required to
reassemble the display module.
Revision 13
25. Loosen the End Cap Lock, and unscrew the End Cap from the electronics
Replacement
ST 700 SmartLine Pressure Transmitters User's Manual
Page 95