Table 4.2 Primary Operation Test (Drive B)
Set the HAND-OFF-AUTO switch to "OFF".
Set the MAN-FAULT XFER-AUTO switch to "MAN" for manual.
Set the DRV A-AUTO-DRV B switch to "DRV B".
SET THE HAND-OFF-AUTO switch to "HAND" to start the drive and control drive operation. Use the
keypad to adjust manual speed reference.
Do the normal startup procedure (check rotation direction, check damper position if necessary, set min/
max speeds and accel/decel times, etc.).
When commissioning is complete, set the HAND-OFF-AUTO switch to "OFF" to stop the drive.
Table 4.3 Expanded Function Test
Check AUTO control for correct operation.
Set the HAND-OFF-AUTO switch to "AUTO".
When you will use the Building Automation System (BAS) to select Drive A or Drive B, set the DRV
A-AUTO-DRV B switch to "AUTO".
When you will NOT use the BAS to select Drive A or Drive B, set the DRV A-AUTO-DRV B switch to
"DRV A" or "DRV B" to manually select each drive..
Confirm that you can use the BAS to start and stop Drive A and Drive B in AUTO.
Confirm that you can use the BAS to change the speed reference for Drive A and Drive B.