Location

The refrigerated merchandisers have been designed for
use only in air conditioned stores where temperature and
humidity are maintained at or below 75°F and 55% relative
humidity. DO NOT allow air conditioning, electric fans, ovens,
open doors or windows (etc.) to create air currents around
the merchandiser, as this will impair its correct operation.
DO NOT place Self Contained versions
of this case, having the electric evaporator pan,
underneath or adjacent to any flammable structure
or structure housing flammable merchandise!

Uncrating the Stand

Place the fixture as close to its permanent position as
possible. Remove the top of the crate. Detach the walls
from each other and remove from the skid. Unbolt the case
from the skid. The fixture can now be lifted off the crate
skid. Lift only at base of stand!

Exterior Loading

These models have not been structurally designed to
support excessive external loading. Do not walk on their
tops; This could cause serious personal injury and damage
to the fixture.

Setting and Joining

The sectional construction of these models enable them to
be joined in line to give the effect of one continuous display.
A joint trim kit is supplied with each joint.
This equipment is to be installed
to comply with the applicable
NEC,Federal, State ,and Local
ATTENTION
Plumbing
INSTALLER
Code

Leveling

IMPORTANT! IT IS IMPERATIVE THAT CASES BE
LEVELED FROM FRONT TO BACK AND SIDE TO SIDE
PRIOR TO JOINING. A LEVEL CASE IS NECESSARY
TO INSURE PROPER OPERATION, WATER DRAINAGE,
GLASS ALIGNMENT, AND OPERATION OF THE HINGES
SUPPORTING THE GLASS. LEVELING THE CASE
CORRECTLY WILL SOLVE MOST HINGE OPERATION
PROBLEMS.
NOTE:
A. To avoid removing concrete flooring, begin lineup
leveling from the highest point of the store floor.
B. When wedges are involved in a lineup, set them first.
and Construction
ha ving
jurisdiction.

Installation

All cases were leveled and joined prior to shipment to
insure the closest possible fit when cases are joined in
the field. When joining, use a carpenters level and shim
legs accordingly. Case must be raised correctly, under legs
where support is best, to prevent damage to case.
1. Check level of floor where cases are to be set.
Determine the highest point of the floor; cases will
be set off this point.
2. Set first case, and adjust legs over the highest part
of the floor so that case is level. Prevent
damage - case must be raised under leg or by use
of 2x6 or 2x4 leg brace. Remove side and back leg
braces after case is set.
3. Set second case as close as possible to the
first case, and level case to the first using the
instructions in step one.
4. Apply masking tape 1/8" in from end of case on inside
and outside rear mullion on both cases to be joined.
METHOD: RGD/RGDC ALIGNMENT FOR LINE UPS
1. Surface must be clean, dry, and free of debris. Apply
Devan Sealant to RGDC case sides along joint
faces.
(See Figure 1)
2. Identify Alignment/Bolting points provide as shown.
(See Figure 1)
3. Align and adjoin cases in line up configuration.
4. Bolt cases together at Alignment/Bolting points
using provided hardware or equivalent hardware.
BOLT HEX HEAD 3/8-16 X 3/4"
NUT TOP LOCK 3/8-24 ZINC
Devan Sealant 255-2
5. Once bolting is complete. Apply silicone to wrapper
case joints. (See Figure 1)
5