Commissioning Procedure - Siemens SIMATIC S7-1500 System Manual

Automation system
Hide thumbs Also See for SIMATIC S7-1500:
Table of Contents

Advertisement

Commissioning

9.3 Commissioning procedure

9.3
Commissioning procedure
Requirement
The following requirements must be met:
● CPU that is in the "Factory settings" state or has been reset to Factory settings
(Page 139)
● SIMATIC memory card that is in the delivered condition and formatted
Commissioning procedure
For the first commissioning of an S7-1500 automation system, we recommend the following
procedure:
Action
Configure hardware in STEP 7 and
perform power balance calculation (see
also "Special considerations: CPU as
bus device")
Create user program
Insertion of all required modules
Wiring of the assembly (power supply
modules, front connectors, ...)
Insertion of the SIMATIC memory card
into the CPU
First power-on
LED check
Evaluate information on the CPU's
display
Configure hardware in STEP 7 and
upload to the CPU
Test the inputs and outputs
108
Remark
See the section Power balance calculation (Page 43).
See the STEP 7 online help
See the Installation (Page 46) section
See the Wiring (Page 59) section
See the section, Insertion/removal of the SIMATIC memory card (Page 110)
Switch on the CPU and power supply module. See the First power-on
(Page 112) section
Notes on the meaning of the LEDs can be found in the manuals of the modules,
and in the System Diagnostics Function Manual
(http://support.automation.siemens.com/WW/view/en/59192926).
See the section, Display of the CPU (Page 156)
See Online and Diagnostics functions in STEP 7
The following functions are helpful: Monitoring and controlling tags, testing with
program status, forcing, controlling the outputs in STOP mode. See the Test
functions and fault resolution (Page 143) section