Transient overvoltages
Take measures to prevent transient overvoltages of more than 40% of the rated voltage (or
more than 119 V). This is the case if you only operate devices with SELV (safety extra-low
voltage).
Suitable cables at high ambient temperatures in hazardous area
If the device is operated at max. ambient temperature, only use cables with permitted
maximum operating temperature of at least 90 ℃. The cable entries used on the enclosure
must comply with the IP degree of protection required by EN IEC / IEC 60079-0, GB 3836.1.
6.1

Procedure for commissioning

Commissioning the PROFIBUS OBT involves the following steps:
• Mounting the PROFIBUS OBT;
• Connecting the power supply;
• Connecting the optical bus cables;
• Connecting the electrical RS-485 bus cable.
6.2

Installation

Mounting the PROFIBUS OBT
The PROFIBUS OBTs can be mounted either on a 35 mm DIN rail with a height of 15 mm
according to DIN 50 022 - 35 x 15 or directly on a flat surface.
1. Install the device so that the climatic limit values in the technical specifications are adhered
to.
2. Make sure that there is adequate space to connect the bus and power supply cables.
3. Mount the modules only on a rail or mounting plate that is grounded with low resistance and
inductance. When securing the module to a mounting plate, run a cable from the grounding
terminal of the OBT to the nearest possible ground, keeping the cable as short as possible.
Mounting on a DIN rail
Fit the upper catch of the module over the DIN rail and push in the lower part of the module as
shown in Figure 5-1 until it clicks in place.
PROFIBUS Optical Bus Terminal (OBT)
Operating Instructions, 06/2022, C79000-G8976-C122-08
WARNING
WARNING
Commissioning
6.2 Installation
25

Advertisement

Table of Contents
loading

Table of Contents