CHECKLIST

FINAL CHECKLIST
The checklist is ONLY to be completed by an Authorised Person.
IMPORTANT
Check Item
Is the indoor unit installed securely?
Has an inspection been made to check for gas leakage?
Has all thermal insulation been completed (vapour pipes,
liquid pipes, indoor portions of the drain hose extension)?
Is the drainage secure?
Are the electric wires installed correctly?
Is the wiring in accordance within the specifications?
Are all inlets / outlets of the indoor and outdoor units free of
any obstructions?
Are the stop valves open?
Are the pipes designed for use with R32?
Has a leak test been carried out for the pipe connections?
Has air purging been carried out?
Has the appliance been tested for correct operation?
Is the end user fully aware of the operating procedure?
If you have answered no to any of the above, you must check and correct before appliance hand-over to customer.
Rinnai
What can happen if not checked
Falling, vibration, noise
No cooling or heating
Condensation
Water leakage
No cooling or heating, may cause electrical shock or
electrical fire.
Operation failure, electrical fire
No cooling or heating
No cooling or heating
Pipe or pipe connection leakage
Pipe connection leakage
No cooling or heating
No cooling or heating
Incorrect operation