● Inspect running restrictions, evaporator and condenser side temperature settings,
and delays in restart.
● Inspect suction and discharge pressure switch, bars.
● Perform compressor load control functional test.
● Test electrical cabin fan and filter, also for possible variable frequency drives.
● Check refrigerant and oil quantity.
● Perform moisture check.
● Check compressor and piping installation.
● Inspect cable shoe and terminal block connections also with a thermal camera.
● Perform leakage test and repair possible leakages. Perform the leakage test
according to the Heat pump leakage check list of the Commissioning report.
Verifying certificates, documents, and approvals
● Make sure that the pre-commissioning certificate is completely filled and signed by
the person responsible for the installation.
● All required control documents regarding the installation are in order, including leak
and pressure test of water piping, and electrical supply certificate.
● Electrical feed approved by the customer to be taken into operation.
● Hot and cold water systems approved by the customer for operation.
● Ethernet communication, if any, approved to be used.
● Site manager/customer approval for start of commissioning.
EXEP01 2150EN
Once installation and commissioning are complete, fill out the
installation and warranty reports.