Master FFLS325 Operation Manual page 17

Laser screed

Advertisement

1) As it is shown in Pic 5.3, two receivers are fixed to the two
aluminum poles.
2) In the case of the transmitter is installed, aim first handheld
receiver at transmitter height, make the bottom end of the rod
touch just touch the concrete surface, and then adjust the height
of the receiver so that the center position of the transmitter laser
beam alignment.
3). Put the handheld receiver on one side of the blade
perpendicularly, adjust electric cylinder manually until the
digital display of handheld receiver is "0", that is, the handheld
receiver lever aligned with the central position of
the laser beam emitter again. (Note that both of the sides shall be
adjusted as above-mentioned.)
4) Finally adjust the two receivers on the aluminum poles to aim
their center at the transmitter beams.
(II). Generators starting
1) Open fuel plug,see Pic 5.4
Tel:(+86)17737606271