Master FFLS325 Operation Manual

Master FFLS325 Operation Manual

Laser screed

Advertisement

Quick Links

OPERATION MANUAL
FFLS325 Laser Screed
P E R F O R M A N C E · E F F I C I E N T · R E L I A B L E
Master sincerely thanks you for selecting the Plate
Compactor Machine. For your Safety and proper
operation, before you start to operate or carry out any
maintenance on this equipment, YOU MUST READ
and STUDY this manual carefully. Be sure to always
keep it ready for reference.

Advertisement

loading

Summary of Contents for Master FFLS325

  • Page 1 P E R F O R M A N C E · E F F I C I E N T · R E L I A B L E Master sincerely thanks you for selecting the Plate Compactor Machine. For your Safety and proper...
  • Page 2: Table Of Contents

    Produced By Henan Master Machinery Co.,Ltd Dear Customer, Thanks for choosing Master machine. To ensure the safety and proper use of the machine, please read the instruction book carefully before use. Also, please fill this card and save it for warranty use.
  • Page 3 2. Generators inspection before operation…………………………….5 4.2 Laser system ……………………………………………………6 1.Specifictions of laser transmitter ……………………………………6 2. Keys on transmitter(Pic 4.3)…………………………………….6 3.Specifications of laser receiver ……………………………………7 4.Keys on receiver(Pic 4.5) ……………………………………8 4.3Switches on control panel …………………………………………8 V.Operations …………………………………………………………10 5.1Start the machine ………………………………………………10 1.Preparations before starting …………………………………………10 2.Start procedure ……………………………………………………11...
  • Page 4: Foreword

    Foreword Thank you for using LS-325 laser concrete leveling machine: LS-325 laser concrete leveling machine is mainly used for road construction and ground leveling. It uses advanced laser control technology, computer control technology, sensor technology, servo drive technology and much other high-end technology with a high degree of automation, simple operation, small construction workers, low cost, high efficiency, good quality and other advantages.
  • Page 5: I.machine Structure

    Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Machine Structure Pic 1.1 Laser screed Pic 1.2 Transmitter...
  • Page 6 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com As it is shown in Pic 1.1, the machine can be divided into two parts as below. Vibrating leveling part: vibration motor, vibration plate, blade and laser receiver, etc. Power part: Control panel, generators, control systems and drive assembly etc.
  • Page 7: Application

    Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 3.1 Application All kinds of concrete floor(including industrial floor with reinforcing mat) Construction conditions: 1) concrete slump 90 ~ 150mm 2) base roughness ≤100mm 3.2 Performance (1) Ground Flatness: ≤±4mm/2m (2) The ground elevation error: diameter range≤±7mm/100m...
  • Page 8 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Max. output (KVA) Rated output (KVA) Generator Type 4-cycle air-cooled OHRV Rated power (KW/rpm) 4.8/3600 Displacement (cm3) Others Fuel 93# unleaded gasoline Size(L×W×H)(mm) 623×438×491 Net weight (kg) Starting mode Manual Fuel tank (L) Oil specification /capacity (L) SAE 10W-30/ 0.6L...
  • Page 9 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Stop generators and open the cap. Apply 93# gasoline. Please turn off the fuel plug before adding fuel.(Pic 4.2) The fuel shouldn’t go above the top of the filter when adding it. Tight the fuel cap clockwise after adding fuel Please clean the fuel splashed.
  • Page 10 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 1. Specification of transmitter Item Transmitter Precision ±1.9mm/50m Automatic adjusting angle ±3° Application range 2~700m Within 2min (Please reset the transmitter if no Automatic correction time correction in 2min NI-MH battery BT-49Q (chargeable, working Current source time about 60hr)...
  • Page 11 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 2.Keys on transmitter(Pic 4.3) Pic 4.3 Structure of Transmitter (1) Press the power button shortly to light the power indicator, then the laser transmitter starts. (2) If the power light flashes after the laser is activated, it shows that the battery is low and you shall replace it.(Pic 4.4)
  • Page 12 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Pic 4.4 Charge indicators 3. Specification of receiver Item Receiver Detecting width 250mm Detecting direction 360°(horizontal) Mode 1:±3mm;Mode 2:±6mm;Mode Detecting precision 3:±15mm;Mode 4:±30mm(Mode 1 is default, which can’t be changed by users) Application range...
  • Page 13 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 1. Receiver has a battery slot for 2# batter, which is useless. 2. Power must be cut when pulling or inserting the air plug. 3. Adjust the height of the receiver manually. 4.3 Switches on Control Panel...
  • Page 14 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Pic 4.6 control panel Switches on the control panel(Pic 4.6) Item Function Power switch Master switch Emergency switch Emergency stop Switch of LED Control LED light Forward/back Control the machine forward or back...
  • Page 15 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Check the battery power Installed laser transmitter correctly Installed laser receiver correctly Chart 5.1 Preparations before starting 2. Starting procedures (I) Installation and starting of transmitter and receiver (1) Installation of transmitter(Pic 5.1、5.2)...
  • Page 16 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Pic 5.2 Installation of transmitter 2). Fix the transmitter to the tripod platform 3). Adjust the height of the tripod platform (≥1.8m) and press the switch to start the transmitter. (Note: After a few seconds the transmitter will automatically adjust the leveling, the laser turns off, and then turns on automatically after about 30s).
  • Page 17 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Pic 5.3 Installation of receiver 1) As it is shown in Pic 5.3, two receivers are fixed to the two aluminum poles. 2) In the case of the transmitter is installed, aim first handheld...
  • Page 18 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Pic 5.4 fuel plugs stop switch on 2) Turn the arrow on stop switch of generations to ON, see 5.5 Pic 5.5 stop switch of generators 3) Pull throttle switch on generators ( turn on it according to the specific temperature.
  • Page 19 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com shutdown); (III) Open the key switch on the operation frame 5.7 power switch of the operation frame (IV). Use the function keys to operate the machine ( Key introduction in page 10) (V). Clench the security armrest in the left hand to control the machine walking.
  • Page 20 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 5.2 Automatic mode/Manual mode of machine 1. Manual mode operation instructions “Manual/Automatic” selector switch on the operation frame,corresponding to “upper eft/left (1). lower”“upper right/low right”和“up/down” those three switch。 (Drawing the corresponding range with yellow line in the operation frame), as picture 5.10:...
  • Page 21 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com manual) (3). When the “Manual/Automatic” in the right yellow part to “Manual” place, the motor “up/down” to control the linear actuator in the front of the machine, up and down the vibration leveling plate(Attention: need press the handles, that will come when the machine is not move;...
  • Page 22 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com of the machine.) 5.11 Forward/backward and speed switch 3. Driving the machine to the construction region, then put the machine to the initial position, and then turn the walking direction knob to the...
  • Page 23 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 5.4 Machine stop 1. Shut off all the switch or in the “manual”; 2. Shut off the key. 3. Shut off the output switch of the generator。 4. Turn the switch of the generator to the OFF.
  • Page 24 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com (5). Please check if the screws and the coupling of the oil hose loose or not after working. (6). Please use the rain wear when put outdoor in the rain day. (7). Please package all plug with plastic wrap, to prevent water or knock against.
  • Page 25 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com (3). Please try to charge after the battery power is completely used up. Ensure as far as possible when charging a full, do not outage of the power。 (The first charge time is suggest to be 12 hours, afterwards will be 8 hours.
  • Page 26 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 7.1 Machine wheel 7.2Transportation: (1). Pave the ramp on the end of the truck, and keep them fastness. (2). Make sure all the switch are shut down (3). Assemble the wheels in the rear side of the machine.
  • Page 27 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 7.2 Machine loading (6). Put the other parts on the truck, and fasten them. (7). Suggest to using the rain cloth to package the machine when transporting.
  • Page 28 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com (8). Package the plug with the plastic wrap, to prevent water or knock against. (9). For short distance, please move follow as the step 4。 VIII. ATTENTION Please confirm that you have carefully read and understand the following matters 8.1Attention matters when operation:...
  • Page 29 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 8.2:Attention matters when working 1. When working, It is,the concrete leveling process(refers to the leveling line under the machine effective width) should not interrupt and need to finish one time. 2. When a temporary pause, need to shut off the vibration motor first.
  • Page 30 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com 2. Need to change the engine oil, every 100 hours working time. IX. The common failures and solutions The Emitter cannot be started Reason: :out of power。 Solution:Change the new battery. 3. Emitter discontinuous, intermittent emission light beam Reason:The machine transmitter with automatically leveling, if the...
  • Page 31 Henan Master Machinery Co., Ltd Tel:(+86)17737606271 www.mastermachinerys.com Solution:Suggest to use the concrete vibrator, then use the machine to leveling. 4.The ground plane less than expected value after leveling. Reason:With different slump concrete, the after vibrating concrete slump is different. Solution:Adjust leveling elevation according to the worker’s experience.