Commissioning; Softener Commissioning; Water Filling, Draining And Waterproofness Inspection - Pentair EVOLIO 255 740 Installer Manual

Table of Contents

Advertisement

6

Commissioning

6.1

Softener commissioning

6.1.1

Water filling, draining and waterproofness inspection

Once the previous initial programming steps are performed, that the softener is in place and
hydraulically connected to the main water line (see Softener installation [
be started up.
CAUTION
Do not rotate the camshaft by hand or damage to the unit may occur. Use the controller
to take the camshaft electronically through the cycles.
Follow these steps carefully:
1. With the main water supply closed, open the nearest faucet downstream the unit and the
upper one on the line if not still open from installation step (see Softener installation
[
Page 30]).
2. With the supply water for the system still turned off, position the bypass valve to the
"nonbypass" (normal operation) position for the inlet side, while the outlet stay in bypass
position.
3. Press
on the controller for 5 seconds. This will initiate a manual regeneration. The
controller will indicate that the motor is turning the camshaft to cycle C1 (Backwash) position
by flashing an hourglass. The controller will display the total regen time remaining. If you
press and hold the
cycle.
4. Fill the media tank with water.
ð While the controller is in cycle C1 (Backwash), open the water supply valve very slowly to
approximately the ¼ open position.
CAUTION
If opened too rapidly or too far, media may be lost out of the tank into the valve or the
plumbing. In the ¼ open position, you should hear air slowly escaping from the valve
drain line.
Ref. MKT-IM-037 / D - 25.10.2021
In
button, the controller will indicate the time remaining in the current
Installer manual Evolio 255 740-760 - Commissioning
Out
Page 30]), the unit can
49 / 90