ABB Relion 670 Series Commissioning Manual page 91

Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

1MRK 511 403-UUS Rev. K
IEC15000024 V1 EN-US
The Signal Monitoring menu changes and indicates the forcing values that can be edited.
IEC15000025 V1 EN-US
5.
Select and edit the values.
6.
Click Acknowledge and send.
IEC15000026 V1 EN-US
This commits the values to the IED and exits the editing session.
7.
Click Cancel to abort the changes and revert back to actual IED values.
IEC15000032 V1 EN-US
To force more signals, click the button Start editing signal value for forcing again.
Bay control REC670
Commissioning manual
Regardless if the forcing changes are commited or canceled, the forcing is still active.
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Section 10
Testing IED operation