Section 12
Primary injection testing
3.
In this view, check the following settings:
3.1. Check that Control Mode is set to Manual.
3.2. Operate the tap changer so that the Load Voltage corresponds to the Voltage Set Point.
3.3. Check that neither the Raise or the Lower command are operating. Voltage Deviation should
3.4. Compare the values of Bus Voltage and Load Voltage.
For inductive load, the Bus Voltage should be higher than the Load Voltage. If not, current circuits are
incorrect and must be reversed. Incorrect current polarity may be an issue with physical wiring or the
current direction convention selected for the CT analogue input as part of the setting in the PST setting.
12.1.2

Voltage control of Parallel Transformers

In parallel operation, each transformer protection IED must be connected to the station communication
bus for data exchange. The following procedure assumes that the necessary pre-configuration in the
Parameter Setting tool and the Signal Matrix tool has been performed and tested to enable data
exchange between IEDs or between instances of voltage control in the same IED.
218
be less than 100%.
UL can be obtained by a vector calculation where IL is the load current and values for RL and
XL are the settings given in primary system ohms.
~
© 2017 - 2021 Hitachi Power Grids. All rights reserved
IEC13000251-1-en.vsd
X
R
L
L
V
B
V
B
jX
I
V
L
L
L
Re
R
I
L
L
ANSI06000487-2-en.vsd
1MRK 511 403-UUS Rev. K
SEMOD176327-186 v5
Bay control REC670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion rec670

Table of Contents