ABB Relion 670 Series Commissioning Manual page 143

Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

1MRK 511 403-UUS Rev. K
2.
Values of the logical signals and the service values for SCCFPVOC (51 V) are available on the
local HMI under: Main menu/Tests/Function status/Unbalance protection/
CapBankCascadingFail(51V,2(I>/U<))/SCCFPVOC (51V, 2(I>/U<)):x, where x = instance number.
3.
Set the constant input voltage as, VA = 63.5∠0° V, VB = 63.5∠240° V, and VC = 63.5∠120° V in
secondary at rated frequency.
4.
Set the constant input current as, IA = 0∠0° A, IB = 0∠240° A, and IC = 0∠120° A in secondary at
rated frequency.
5.
Following are the steps to check the operation of Step 1.
Step
No.
5-a
5-b
5-c
6.
Repeat
values of input currents as per slope characteristics and the VDepFact2 based on the I>> value;
check the output PU_ST2 and BFI_3P.
Verification of zero sequence-based operation
1.
Set the following parameters:
Bay control REC670
Commissioning manual
VoltageInput = negSeq
I > = 125% IBase
VDepFact1 = (1-117)/I> = 0.064
The Base values, CT and VT ratios are as follows:
2.1. VBase considered is 400 kV
2.2. IBase considered is 3000 A and the calculations are done considering CT
ratio as 3000 A/1 A and VT ratio as 400 kV/110 V
2.3. Rated frequency = 50 Hz
Step1 operating characteristic verification
Inject constant voltages of VA = 1.0∠0° V, VB = 1.0∠120° V,VC
= 1.0∠240° V and constant currents of IA = 0.10∠0° A, IB =
0.10∠120° A, IC = 0.10∠240° A in secondary at rated
frequency.
Repeat
Inject constant voltages of VA = 57.73∠0° V, VB = 57.73∠120°
V, VC = 57.73∠240° V and constant currents of IA = 1.10∠0° A,
IB = 1.10∠120° A, IC = 1.10∠240° A in secondary at rated
frequency.
Repeat
Inject constant voltages of VA = 76.21∠0° V, VB = 76.21∠120°
V, VC = 76.21∠240° V and constant currents of IA= 1.26∠0° A,
IB = 1.26∠120° A, IC = 1.26∠240° A in secondary at rated
frequency.
Step
3,
Step 4
and
Step 5
Operation = Enable
Operation1 = Enable (Step 1)
CurrentInput = 3×ZeroSeq
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Step 3
and
Step
4, to reset PU_ST1 and BFI_3P.
Step 3
and
Step
4, to reset PU_ST1 and BFI_3P.
for Step 2 operation, by setting Operation2 (Step 2) Enable, new
Testing functionality by secondary injection
Expected output
PU_ST1 and BFI_3P signal should
be TRUE
PU_ST1 and BFI_3P signal should
be TRUE
PU_ST1 and BFI_3P signal should
be TRUE
GUID-8EAE0867-4161-4BFF-AE89-BE44F374B6A1 v1
Section 11
137