Siting and levelling the boiler
Fig. 5
Level the boiler horizontally. No special foundations
are required.
Note
Adjustable feet or adjustable screws with locking nuts
can also be inserted into the holes ( 7 12 mm) in the
base rails (not included in the delivered condition).
1.
Note
We recommend installing the boiler on anti-vibration
boiler supports
(see page 6).
C
In order to load the spring elements evenly, floor undu-
lations should not be more prominent than 1 mm.
Arrange the boiler supports underneath the boiler.
Position the supports centrally underneath the base
rails.
When the boiler is set down, single boiler supports
may temporarily be overloaded. To aid installation,
support the boiler on 3 timbers (
these at the front, centre and end of each boiler sup-
port.
35 mm). Position
□