Siting and levelling the boiler
!
Please note
Damage to the flue gas connection can result in
leaks.
Never lift or move the boiler by the flue gas con-
nection.
Fig. 4
Level the boiler with its adjustable feet.
Note
Extend the adjustable feet until the castors are free of
load.
If a neutralising system is being fitted, wind out the
adjustable feet as far as possible.
±15mm
Note
A suitable condensate drain must be available in the
installation room if the boiler is installed at ground level
(max. 50 mm above the floor).
Note
Special foundations are not required.