SECTION 3 – HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
Rigging and lifting should only be done
by a professional rigger in accordance
with a written plan. The most appropriate
rigging and lifting method will depend on
job specific factors, such as the equipment
available and site needs. Therefore, a
professional rigger must determine the
rigging and lifting method to be used. It is
beyond the scope of this manual to specify
rigging and lifting details.
JOHNSON CONTROLS
This chiller-heater is for air conditioning or cooling a
manufacturing process. Transport, store, and use this
chiller-heater under the following conditions:
• Installation location: Indoor, non-explosion area
• Ambient temperature: 10 ~ 40 °C
• Humidity: 10 ~ 90% (RH%)
• Altitude: 1000 m or lower
If the plant room temperature will ever drop below 10
°C, you must have the cold ambient option.
Outdoor installation is not recommended.
If you do install the unit in an outdoor
location, be sure to keep all access doors
and windows closed. Rain and pollutants
will cause problems if they get into the
unit.