Actions To Take Against Power Failure; Figure 46 - Actions To Take Against Power Failure - York YHAU-CE Installation Operation & Maintenance

Double-effect exhaust gas absorption chiller-heater
Table of Contents

Advertisement

SECTION 8 – TROUBLESHOOTING

ACTIONS TO TAKE AGAINST POWER FAILURE

If the main power fails, take the following actions.
Re-start using the Control Panel
located on the chiller-heater. Monitor
until chiller-heater returns to normal
operation. Purge directly from the
absorber. Stop the machine to ensure
the dilution operation takes place. The
dilution operation takes approximately
15 minutes.

FIGURE 46 - ACTIONS TO TAKE AGAINST POWER FAILURE

124
Chiller-heater stops
Power is restored
Power failure interval is shorter
than the controller back up interval
Power failure interval is shorter
than 5 minutes
Yes
Power failure interval is shorter
If the power is not restored within 5
hours, the solution in the unit may be
crystallized. Contact your local Johnson
Power failure
No
No
than 1 hour.
No
FORM 155.35-ICOM2.EN.CE/GB (1018)
DATE: 10/30/2018
Yes
Continue running machine
Yes
Re-start using the Control Panel
located on the chiller-heater. Monitor
until chiller-heater returns to normal
operation. Purge directly from the
absorber.
LD26805
JOHNSON CONTROLS

Advertisement

Table of Contents
loading

Table of Contents