PACD011001G2 / PACD011004G3
2. After piping, check to make sure draining flows smoothly.
WHEN ELECTRIC WIRING WORK IS FINISHED
Check drainage flow during COOL running, explained under "TEST OPERATION".
WHEN ELECTRIC WIRING WORK IS NOT FINISHED
Remove the electric parts box lid, connect a power supply and remote controller to the terminals.
Next, press the inspection/test operation button "
test operation mode. Press the operation mode selector button "
"
that the water has drained from the unit. Press "
Urban Multi Inverter "MX1" Series
Open the water inlet lid, add approximately 1000 cc of water gradually and check drainage flow.
". Then, press the ON/OFF button "
" on the remote controller. The unit will engage the
" until selecting FAN OPERATION
". The indoor unit fan and drain pump will start up. Check
" to go back to the first mode.
Installation 1
33