7.4 Location requirements — ACU
The installation location must take into account the following requirements:
• ACU-200, ACU-300, ACU-400 — install below decks in a dry area.
• ACU-100, ACU-150 — install above or below decks.
• The unit should be mounted on a vertical surface.
• The unit should be located as close to the battery as practical.
• Choose a location where the unit will be safe from physical damage and excessive vibration.
• Choose a location where the unit will not be subjected to a load or force.
• Mount away from any source of heat or potential flammable hazards, such as fuel vapor.
• The unit should be mounted in a location where the diagnostics LED is viewable.
Location requirements