Commissioning & Starting the Shower
WARNING! For the Pumped low pressure valve you must follow the separate valve
commissioning sequence in the section below.
1
Turn on the water supply and open water inlet supply isolators.
2
Turn on the electrical supply to digital mixing valve.
The digital mixing valve will power and perform a self check where the LED will indicate
a RED light initially and will then change to BLUE light after a few seconds.
Note: If the LED does not turn to a solid BLUE light after 10 seconds, indicating
the product is ready to use, refer to the troubleshooting or fault diagnosis section.
Power Indication
LED
35