Start Up and Commissioning

3 Start Up and Commissioning

3.1 Pre-start

CAUTION
Before applying power to the unit, inspect the entire
installation as detailed in Table 3.1. Check mark those items
when completed.
Inspect for
Description
Auxiliary equipment
Look for auxiliary equipment, switches, disconnects, or input fuses/circuit breakers that may reside
on the input power side of the frequency converter or output side to the motor. Ensure that they
are ready for full speed operation.
Check function and installation of any sensors used for feedback to the frequency converter
Remove power factor correction caps on motor(s), if present
Cable routing
Ensure that input power, motor wiring and control wiring are separated or in three separate metallic
conduits for high frequency noise isolation
Control wiring
Check for broken or damaged wires and loose connections
Check that control wiring is isolated from power and motor wiring for noise immunity
Check the voltage source of the signals, if necessary
The use of shielded cable or twisted pair is recommended. Ensure that the shield is terminated
correctly
Cooling clearance
Measure that top and bottom clearance is adequate to ensure proper air flow for cooling
EMC considerations
Check for proper installation regarding electromagnetic compatibility
Environmental consider-
See equipment label for the maximum ambient operating temperature limits
ations
Humidity levels must be 5-95% non-condensing
Fusing and circuit
Check for proper fusing or circuit breakers
breakers
Check that all fuses are inserted firmly and in operational condition and that all circuit breakers are
in the open position
Earthing (Grounding)
The unit requires an earth wire (ground wire) from its chassis to the building earth (ground)
Check for good earth connections (ground connections) that are tight and free of oxidation
Earthing (grounding) to conduit or mounting the back panel to a metal surface is not a suitable
earth (ground)
Input and output power
Check for loose connections
wiring
Check that motor and mains are in separate conduit or separated screened cables
Panel interior
Inspect that the unit interior is free of dirt, metal chips, moisture, and corrosion
Switches
Ensure that all switch and disconnect settings are in the proper positions
Vibration
Check that the unit is mounted solidly or that shock mounts are used, as necessary
Check for an unusual amount of vibration
Table 3.1 Start Up Check List