Convenience Receptacle/Section Lights

A Ground Fault Circuit Interrupter (GFCI) convenience
receptacle is provided in the main control box on all units. The
receptacle can either be field powered or unit powered. If it
is field powered, a field wired 120V circuit must be provided.
Refer to the
Field Power Wiring
receptacle is unit powered, then no additional field wired 120V
circuit is required for it function.
If the optional service lights were included, the light switch will
be located near the GFCI receptacle. The lights are always
powered by the same source as the GFCI; either unit powered
or Field powered depending on the GFCI option selected.

Check, Test and Start Procedures

LOCKOUT/TAGOUT all power sources before servicing this equipment.
More than one disconnect may be required to de-energize unit.
Electric shock and moving components such as, fans, dampers, energy
recovery devices can cause serious injury, death and property damage.
All start-up and service work must be performed only by trained, experienced
technicians familiar with the hazards of working on this type of equipment.
Read and follow the all relevant manuals before operating or servicing.
Bond the equipment frame to the building electrical ground through
grounding terminal or other approved means.
All units are complete an end of line operation test at the
factory to promote proper operation in the field. Nevertheless,
the following check, test, and start procedures must be
performed to properly start the unit. To obtain full warranty
coverage, complete and sign the check, test, and start form
supplied with the unit, or complete the
Warranty Registration Form" on page 110
Daikin.
A representative of the owner or the operator of the equipment
should be present during start-up to receive instructions in the
operation, care, and maintenance of the unit.
www.DaikinApplied.com
section for more details. If the
DANGER
"Rooftop Equipment
and return it to
Servicing High Voltage Control Panel
Components
LOCKOUT/TAGOUT
all power sources prior to servicing the unit.
Hazardous voltage may cause serious injury, death, and property damage.
Disconnect electric power before servicing equipment. More than one
disconnect may be required to de-energize the unit.
Disconnect all electric power to the unit when servicing control
panel components. Unless power is disconnected to the unit,
the components remain energized. Always inspect units for
multiple disconnects to ensure all power is removed from the
control panel and its components before servicing.
Before Start-up
1. Verify that the unit is completely and properly installed
with ductwork connected.
2. Verify that all construction debris is removed, and that
the filters are clean.
3. Verify that all electrical work is complete and properl
terminated.
4. Verify that all electrical connections in the unit control
panel and compressor terminal box are tight, and that the
proper voltage is connected.
5. Verify all nameplate electrical data is compatible with the
power supply.
6. Verify the phase voltage imbalance is no greater than 3%.
7. Verify that gas piping is complete and leak tight.
8. Verify that the shutoff cock is installed ahead of the
furnace, and that all air has been bled from the gas lines.
9. Manually rotate all fans and verify that they rotate freely.
10. Verify all fasteners on the fan assemblies are still tight.
11. Verify that the evaporator condensate drain trap is
installed and that the drain pan is level.
12. If unit is curb mounted, verify that the curb is properly
flashed to prevent water leakage.
13. Before attempting to operate the unit, review the control
layout description to become familiar with the control
locations.
14. Review the equipment and service literature, the
sequences of operation, and the wiring diagrams to
become familiar with the functions and purposes of the
controls and devices.
15. Verify that the crankcase heaters are operating. These
should operate for at least 24 hours before starting the
compressors.
16. Determine which optional controls are included with the
unit.
NOTE: If desired, you can significantly reduce all MicroTech 4
internal control timers by the changing the entry
under keypad menu Main Menu\Commission Unit\
Timer Settings\Startup,Recirculate = (from 180s to
60s min where 60s is the number of seconds you
want the unit to operate with fast timers).
41
Unit Operation