Installation Methods For The Rack To Withstand Earthquakes With An Acceleration Of Up To 10 M/S 2 (1000 Gal) - Fujitsu PRIMERGY 19 User Manual

19-inch rack
Table of Contents

Advertisement

1 Method where the rack is anchored to a stabilizing surface
Install the rack by using the same method described in "3.4.2 Installation methods for the rack to withstand earthquakes with
an acceleration of up to 10 m/s
2 Method where the rack is not anchored to a stabilizing surface
This rack corresponds only to the L-shaped Stabilizer.
Note: The attached stabilizer is a means of preventing the rack from tipping over during device maintenance. If the rack is not
anchored to a stabilizing surface, be sure to attach a stabilizer before installation.
The stabilizer is an optional product (not supplied with this rack).
3.4.2 Installation methods for the rack to withstand earthquakes with an acceleration
of up to 10 m/s
(1000 gal)
2
The rack must be anchored to a stabilizing surface as described below.
1 Securing the rack using the Quake Proof Stabilizer kit
Attach the Quake Proof Stabilizer kit (an optional product that will need to be prepared separately) the rack (front, right, and
left). Then, secure the rack to the slab (building floor) using the holes in the kit.
2 Securing the rack using the leveling feet
Anchor the rack to the slab (building floor) using the M20 screw holes in the ground plate of the leveling feet and M20 bolts
with a length of 17 mm.
(1000 gal)".
2
34