To Check For Leaks; To Perform Vacuum Drying - Daikin R32 Series Installer's Reference Manual

Hide thumbs Also See for R32 Series:
Table of Contents

Advertisement

6.5.3 To check for leaks

6.5.4 To perform vacuum drying

3(A)MXM+3(A)MXF+4MXM+5MXM
R32 Split series
4P600463-1B – 2020.05
NOTICE
Do NOT exceed the unit's maximum working pressure (see "PS High" on the unit
name plate).
NOTICE
Make sure to use a recommended bubble test solution from your wholesaler. Do not
use soap water, which may cause cracking of flare nuts (soap water may contain salt,
which absorbs moisture that will freeze when the piping gets cold), and/or lead to
corrosion of flared joints (soap water may contain ammonia which causes a corrosive
effect between the brass flare nut and the copper flare).
1 Charge the system with nitrogen gas up to a gauge pressure of at least
200 kPa (2 bar). It is recommended to pressurize to 3000 kPa (30 bar) in order
to detect small leaks.
2 Check for leaks by applying the bubble test solution to all connections.
3 Discharge all nitrogen gas.
Connect the vacuum pump and manifold as follows:
a
d
c
b
e
e
i
h
f
g
a
Pressure meter
b
Gauge manifold
c
Low-pressure valeve (Lo)
d
High-pressure valve (Hi)
e
Charging hoses
f
Vacuum pump
g
Service port
h
Valve lids
i
Gas stop valve
j
Liquid stop valve
1 Vacuum the system until the pressure on the manifold indicates −0.1  MPa
(−1 bar).
2 Leave as is for 4-5 minutes and check the pressure:
If the pressure...
Does not change
Increases
3 Vacuum the system for at least 2  hours to a manifold pressure of −0.1  MPa
(−1 bar).
4 After turning the pump OFF, check the pressure for at least 1 hour.
5 If you do NOT reach the target vacuum or CANNOT maintain the vacuum for
1 hour, do the following:
j
h
There is no moisture in the system.
This procedure is finished.
There is moisture in the system. Go
to the next step.
6
Installation
|
Then...
Installer reference guide
41

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents