Procedure
1. Locate the left slide rail. The left mounting slide is stamped with an L identifier on the inside front
location.
2. At the front of the rack, position the left slide rail (C) between the left-side front and rear rack EIA
mounting standards as shown in Figure 4 on page 5.
3. Insert the front slide flange locator studs into the front EIA mounting holes.
Figure 4. Attaching the slide rails at the front of the rack
4. Insert the rear slide flange locator studs on the slide rail into the rear EIA mounting holes.
5. Position the slam-latch bracket (B) to cover the front EIA space of the slide rail as shown in Figure 4
on page 5.
Note: Each side of the slam-latch bracket is marked with an L and an R. Ensure that you position the
R side with the right side and the L side with the left side of the rack.
6. Attach the slam-latch bracket to the front rail flange with one M5 X 16 mm screw (A). Place the screw
in the upper hole of the EIA rack unit as shown in the following figure.
7. Repeat steps "1" on page 5 through "6" on page 5 for the right slide rail (D) as shown in Figure 4 on
page 5. The right slide rail is stamped with an R identifier on the inside front location.
8. Move to the rear of the rack.
9. Working from the rear of the rack, verify that the locator studs have been installed in the correct
holes of the rear EIA vertical mounting standards. If necessary, reposition the slide rail, and close the
mechanism to hold it into place.