Figure 2. Installing the lift handles
2. Align the holes in the lift handles with the six pins on the chassis, and then lift the handle up (B), until
the latches click into place.
Note: Ensure that all six pins are secured.
3. Repeat these steps for all six lift handles.

Installing the server into a rack

You must remove system chassis components so that a minimum of three people can lift it into the rack.
Install the mounting hardware first, then remove components from the system chassis, and then lift the
chassis into place.
Note: You must also attach the system-to-rail locking clips to each rail after placing the system onto the
rails.
The following table lists the removal tasks you must perform so that you can lift the system and install it
into the rack. The number of tasks you must perform is dependent on the number of people you have to
install the rack.
Number of installers
3
Required removal tasks
• System fans
• Front cover
• Power supplies
• PCIe adapters
Installing the IBM Power System E950 (9040-MR9) 3