ZXMBW E9230 User Manual
Steps
60
Confidential and Proprietary Information of ZTE CORPORATION
F
60 F
IGURE
ASTENING
E
ND OF STEPS
VSWR Test
1. After the installation of all antenna feeders and jumpers, con-
duct the
VSWR
test. The VSWR must be less than 1.5.
2. If the VSWR is more than 1.5, check the main antenna and
feeder system, that is:
Check whether the antenna feeders, connectors, and
�
jumpers are intact.
Ensure that the connection between all parts are proper.
�
Check whether the antenna feeder installation is perfect.
�
E
ND OF STEPS
Cabinet Installation Check
Cabinet Installation Check
1. Ensure that cabinet installation location complies with the en-
gineering design drawing.
2. Erect cabinet firmly so as to resist an earthquake measuring
up to 7.0 on Richter scale.
3. Ensure that horizontal and vertical error, and the gap between
adjacent bases are less than 3 mm.