2. Strip off a protective sheath of End B and connect to relevant
3. Bind and fasten the power cable at 0.5 m off the lower con-
4. Perform waterproof processing for the aviation connector.
5. Affix a label with fasteners at two ends of power cable.
E
ND OF STEPS
Installing Grounding Cable
Prerequisites
1. Install the ZXMBW E9230 cabinet.
2. Install the grounding copper bar.
3. Measure the grounding resistance (≤10Ω).
Context
1. The grounding cable is made of fireproof multi-strand conduc-
Steps
1. Copper lugs are crimped at both ends of the grounding cable,
power devices according to the core colors.
nector.
tors. It is in yellow and green and its cross sectional area is
16mm
2
, as shown in
F
42 G
IGURE
ROUNDING
as shown in
Figure
F
43 C
C
IGURE
RIMPING
Confidential and Proprietary Information of ZTE CORPORATION
Chapter 3 Equipment Installation
Figure
42.
C
ABLE
43.
L
OPPER
UGS
49