Section 3 • Scheduled Maintenance Procedures
CHECKLIST B PROCEDURES
B-11
Test the Drive Speed -
Raised or Extended Position
Proper drive function movement is essential to
safe machine operation. The drive function should
respond quickly and smoothly to operator control.
Drive performance should also be free of
hesitation, jerking and unusual noise over the
entire proportionally controlled speed range.
Select a test area that is firm, level
and free of obstructions.
1 Create start and finish lines by marking two
lines on the ground 40 feet / 12.2 m apart.
2 Turn the key switch to platform control and pull
out the red Emergency Stop button to the on
position at both the ground and platform
controls.
3 Raise the primary boom more than
5 feet / 1.5 m.
4 Choose a reference point on the machine; i.e.,
contact patch of a tire, as a visual reference for
use when crossing the start and finish lines.
5 Bring the machine to maximum drive speed
before reaching the start line. Begin timing
when your reference point on the machine
crosses the start line.
6 Continue at full speed and note the time when
your machine reference point passes over the
finish line. Refer to Section 2, Specifications.
3 - 14
B-12
Test the Alarm Package
(if equipped)
The alarm package includes:
· Travel alarm
· Descent alarm
· Flashing beacon
Alarms and a beacon are installed to alert
operators and ground personnel of machine
proximity and motion. The alarm package is
installed on the ground controls side turntable
cover.
1 Turn the key switch to ground controls and pull
out the red Emergency Stop buttons to the on
position at both ground and platform controls.
Result: The flashing beacon should be on and
flashing.
2 Hold the function enable toggle switch to either
side, then move the primary boom toggle switch
to the down position, hold for a moment then
release it.
3 Hold the function enable toggle switch to either
side, then move the secondary boom toggle
switch to the down position, hold for a moment
then release it.
4 Hold the function enable toggle switch to either
side, then move the jib boom toggle switch to
the down position, hold for a moment then
release it.
Result: The descent alarm should sound when
each control toggle switch is held down.
Genie Z-30/20N
April 2005
REV B
Part No. 106373