Section 3: Operation

Light Tower Setup

DANGER
High Voltage. Verify area above unit is clear
of overhead wires and obstructions. Contact
with high-voltage power lines will result in
death or serious injury.
E
A
3. Pull the locking pin (A) on the tongue jack (E) and
rotate the jack 90°. Install the locking pin. Rotate
the jack handle clockwise to raise the trailer tongue
off the towing vehicle.
4. A grounding stud (B) is located on the rear frame of
the trailer near the left side outrigger. For ground-
ing requirements, follow local, state, or National
Electrical Code (NEC) guidelines.
5. See Details C–D. Pull the locking pins (C) on the
outriggers (D) and pull each outrigger out until the
spring loaded locking pin snaps back into place.
Pull the locking pin on the outrigger jack and rotate
each jack 90° so the jack pad is facing down. Install
the locking pin.
Owner's Manual for MLT6SMD Light Tower
NOTE: The mast extends up to 23 ft (7 m).
(000260a)
Figure 3-1. Set Up Outriggers and Jacks
1. For maximum light coverage, position the unit at
ground level or in a spot higher than the area being
illuminated by the lamps.
2. See
Figure
3-1. Place the unit on firm, flat ground,
and block the wheels to prohibit movement. This
will make it easier to level the unit.
C
D
F
B
1"
G
6. See Detail E. Rotate each jack handle clockwise to
start leveling the trailer. Adjust all three jacks by
rotating their handles clockwise until they are firmly
in contact with the ground. Continue until the
wheels are approximately 1 in (2.5 cm) off the
ground (F).
7. If applicable, adjust the lamps prior to raising the
mast. The lamps may be adjusted up, down, left, or
right by simply aiming them in the desired direction.
Operation
DETAIL B
DETAIL C
DETAIL D
006470
DETAIL E
29