Figure 2-20-2
Figure 2-20-3
(2) Checking smooth movement of T1 Boat Unit.
Check X-Value. Check smooth loading and
unloading operations. If not smooth (especially, at
curve of rail), take the following steps.
1. Check deformation of T1 boat joint.
2. If no deformation, then reposition the loading
rail as describe below.
1. Loosen the screw A.
2. While pressing the projection B leftward, tighten
the screw.
If operation is not smooth, remove
CYL and loosen screws A and C.
Turn the rail clockwise as shown in
the figure and then tighten the
screws.
If the rail does not work well, replace it or the T1
boat with a new one.
MECH-48
Figure 2-20-4