Troubleshooting - Baxi EcoBlue Advance 13 Heat ErP Installation And Service Manual

Gas fired wall mounted condensing boiler
Hide thumbs Also See for EcoBlue Advance 13 Heat ErP:
Table of Contents

Advertisement

Baxi EcoBlue Advance 13, 16, 19, 25, 30 Heat ErP Installation Manual
Do not turn either adjustment screw more than 1/8 of a turn at a time. Allow the analyser reading to settle before any further adjustment.
Fig. 63
5.
Press the Chimney Sweep button twice to select the minimum rate. The orange status light for the Chimney Sweep button flashes green briefly and minimum rate is
selected.
6.
Check the CO
is 8.9% ±0.1%. If the CO
2
decrease (4mm hexagon key).
Re-check both the maximum and minimum values if any adjustment has been made.
THERE MUST ALWAYS BE A DIFFERENCE OF 0.4% BETWEEN MAXIMUM & MINIMUM CO
7.
Check the Combustion Performance (CO/CO
8.
Briefly press the RESET button to return the boiler to normal operating status and remove the analyser probe.
Refit the sampling point plug & ensure there is no leakage of products !
Fig. 64
page 57

11 Troubleshooting

11.1 Error Codes
Operation status and error codes are displayed on the 'chimney sweep' button (3) on the control panel. In normal operation this button is illuminated and goes off for a time once
periodically. When normal operation is interrupted for some reason this button will turn off and flash on a number of times periodically. The colour and number of flashes displayed
is dependent on the boiler status or fault condition.
The orange LEDs will flash at EVERY heating demand.
The number of flashes will correspond with the output of the boiler as shown in the table. e.g. 4 orange flashes = 21kW.
This is normal and does not indicate a fault condition.
"Error" or auto reset conditions (Green flashes on "chimney sweep")
The following table describes the conditions that may result in a blocking signal being displayed.
The boiler will try to re-start several times, and normal operation will resume once the blocking condition has been eliminated.
Should the conditions persist the boiler may go into lock-out (see following section)
Status signal
Description
1 flash green
Temperature protection
2 flashes green Shutdown input
50 of 55
is incorrect alter the Offset Adjustment Screw
2
ratio). This must be less than 0.004.
2
Maximum flow temperature exceeded,
Flow temperature rise rate too high,
Excessive difference between flow and
return temperature
BL terminals on User Interaction Controller
are open circuit
http://interpart.partsarena.eu/System/DATA/Dx/DS1/installation/S219/...
(Fig.
64). Turn the screw clockwise to increase the CO
READINGS!
2
Remedial actions by service engineer
Check system circulation & pump operation
Check demands for boiler operation (switched live operation)
Check temperature setting
Check temperature sensors in boiler
If condensate pump is wired to these terminals check
operation of condensate pump
Check wiring to BL terminals (link present or connections
to external device correct)
or anticlockwise to
2
23/01/2018, 11:44