Commissioning; General; Checklist Before Commissioning; Preliminary Electrical Checks - Baxi EcoBlue Advance 13 Heat ErP Installation And Service Manual

Gas fired wall mounted condensing boiler
Hide thumbs Also See for EcoBlue Advance 13 Heat ErP:
Table of Contents

Advertisement

Baxi EcoBlue Advance 13, 16, 19, 25, 30 Heat ErP Installation Manual
1.
Before turning on the electrical and gas supply to commission the boiler, check that all the installation requirements for the chosen heating system and flue options have
been satisfied.
2.
Ensure that the system is vented to expel any excess air.
page 41

7 Commissioning

7.1 General

1.
Reference should be made to BS:EN 12828 & 14336 when commissioning the boiler.
2.
At the time of commissioning, complete all relevant sections of the
3.
Turn the gas supply on and purge according to in GB BS 6891 and in IE I.S. 813 "Domestic Gas Installations".
The combustion for this appliance has been checked, adjusted and preset at the factory for operation on the gas type specified on the appliance data plate.

7.2 Checklist before Commissioning

7.2.1 Preliminary Electrical Checks

1.
Prior to commissioning preliminary electrical system checks should be carried out.
2.
These should be performed using a suitable meter, and include checks for Earth Continuity, Resistance to Earth, Short Circuit and Polarity.

7.2.2 Checks

Check that the boiler has been installed in accordance with these instructions.
Check the integrity of the flue system and the flue seals.
Check the integrity of the boiler combustion circuit and the relevant seals.
Check the integrity of all gas and water joints.

7.3 Commissioning Procedure

CAUTION
On first firing the boiler, an odour may be present for a short period.
1.
Open the main gas supply.
2.
Open the gas cock on the boiler.
3.
Set the controls (thermostats, control system) so that they request heat to turn the boiler on.
4.
The boiler incorporates an automatic air vent. As supplied this is in the open position to allow venting of the system.
page 42

7.4 Gas Settings

7.4.1 "Chimney Sweep" Mode (CSM)
1.
The current operating condition of the boiler is shown by the
frequencies.
2.
Follow the flow chart on the next page to comply with the requirement to check combustion on commissioning.
3.
Setting the boiler to maximum and minimum heat outputs is achieved as follows;
Press the
button for 3 seconds.
CSM is activated and will go to the min rate.
Pressing again will make it adjust to max rate.
To exit press the RESET for 3 seconds.
Fig. 40
After refitting the sampling point plug ensure there is no leakage of products !
page 43
7.4.2 "Chimney Sweep" Mode - Combustion Check
37 of 55
http://interpart.partsarena.eu/System/DATA/Dx/DS1/installation/S219/...
Benchmark Checklist
at the rear of this publications.
button on the User Interaction Controller. The
button can flash in a range of colours and at different
23/01/2018, 11:44

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents