4 COMMISSIONING
4.1
Initial commissioning
Initial commissioning must be performed by a qualified professional.
4.2
Checklist after commissioning
A few days after the appliance is commissioned, please:
Check the installation
●
Check the tightness of the connections
●
Check the water pressure
●
Check that there are no errors on the control panel
●
Inform the user of the frequency of maintenance work to be carried out
●
Explain how the system and control panel work to the users
●
Hand over all manuals to the user
●
4.3
Operating the Unit
Mode #
800W power heating (single tank)
1
1600W power heating (both tanks)
2
Energy saving Active (Temp. = 55°C)
3
Smart control energy Active
4
Anti-legionella mode Active (Temp. = 80°C during 5 min)
5
Reservation
6
Mode description
Mode Active
8
1
7
6
℃
H
2
3
Indicator
Indicator 4 ON
Indicator 5 ON
Indicator 8 ON
Indicator 9 ON
-
Indicator 6 ON
5
4
Fig.7
38