2.3.2
2.3.3
Revised August-2017
Pipe Stand Mounting (FloBoss 103/FloBoss 104)
To install the FloBoss 103/ FloBoss 104 on a 2-inch pipe stand:
1.
Install the pipe stand per the directions included with the pipe stand.
2.
Remove the orifice/meter run from service.
Install the FloBoss on the pipe stand using clamps or mounting
3.
brackets. Refer to Figure 2-4 (for FB103) and Figure 2-5 (for
FB104).
Orifice Plate Mounting (FloBoss 103)
To install the FloBoss 103 on an orifice plate:
1.
Remove the orifice/meter run from service.
2.
Install the FloBoss 103 on the meter run using a manifold and
hardware to secure the FloBoss 103 to the orifice flanges. Refer to
Figure 2-4.
Figure 2-4. FB103 Mounting Options
FloBoss 103/104 Instruction Manual
Installation and Use
2-7