Outdoor Unit
Step
5
Remove the 2 sheets of
putty.
6
There is one nut fixing
the compressor.
Remove the nut with an
open-end spanner.
Before working, make
sure that the refrigerant is
empty in the circuit.
Be sure to apply nitrogen
replacement when
heating up the brazed
part.
Heat up the brazed part
7
of the discharge side
and disconnect (part
"a").
8
Heat up the brazed part
of the suction side and
disconnect (part "b").
9
Lift the compressor up
to remove.