5.4.3

Go online and start the configuration wizard

Procedure with STARTER
Proceed as follows to start configuration of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with
which you wish to go online.
3. Download the hardware configuration found online in
your project (PG or PC).
Significance of the symbol in front of the inverter:
(A) The inverter is online.
(B) The inverter is offline
4. When you are online, double-click on "Control Unit".
5. Start the configuration wizards:
You have started to configure the inverter.
Procedure with Startdrive
Proceed as follows to start configuration of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with which you wish to go online.
3. Once you are online, select "Commissioning" → "Commissioning Wizard":
You have started to configure the inverter.
Converter with control units CU250D-2
Operating Instructions, 04/2015, FW V4.7.3, A5E34261542B AB
5.4 Basic commissioning with a PC
.
Commissioning
73